← All hazard categories

AU hazard library

Demolition of load-bearing structures

Structural demolition + work creating temporary instability. HRCW under WHS Reg 291(1)(c).

Premature structural collapse during demolition

Uncontrolled collapse of load-bearing structure during demolition striking workers or public. HRCW under WHS Reg 291(1)(c) for any demolition of load-bearing element.

Initial risk

EXTREME

L3 × C5

Best residual

MEDIUM

With full hierarchy of controls

HRCW reference

demolition of load bearing structure

Controls (hierarchy of controls order)

  1. Engineering controls

    Residual MEDIUM

    Exclusion zone + perimeter fencing + overhead protection

    Exclusion zone radius = 1.5× height of structure being demolished; 2.4 m construction fencing with shade cloth; overhead public protection where work over footpath; spotters at every entry point.

    Cited: WHS Reg 215 · AS 2601 s 3

  2. Administrative controls

    Residual MEDIUM

    Engineer-designed demolition plan + reverse-engineering

    Demolition plan prepared by a structural engineer detailing sequence (reverse of construction), temporary propping, load paths, exclusion zones and methodology. Plan reviewed daily by site engineer and adjusted as conditions change.

    Cited: WHS Reg 297 · Demolition Work CoP · AS 2601

  3. Administrative controls

    Residual MEDIUM

    Licensed demolition contractor + notification

    Demolisher holds state demolition licence (NSW DE-NS / VIC unrestricted demolition / etc.); regulator notified ≥5 days prior; principal contractor's WHS Management Plan covers the demolition phase.

    Cited: State demolition licensing · Demolition Work CoP s 2

PPE

  • Industrial safety helmetType 1 industrial safety helmet with chin strap where required by site rules or wind exposure. Replace at expiry date or after impact.Standard: AS/NZS 1801
  • Steel-cap safety bootsType 1 safety footwear with steel toecap, slip-resistant sole, ankle support; electrical hazard rating where exposed to live electrical work.Standard: AS/NZS 2210.3
  • Hi-visibility vest or shirt (day use)Class D fluorescent hi-visibility garment for daytime use on site.Standard: AS/NZS 4602.1
  • P2 disposable respiratorP2-rated disposable particulate respirator with fit-check and clean-shaven seal area. Replace when breathing resistance increases or per shift.Standard: AS/NZS 1716
  • Safety glasses (medium impact)Medium-impact safety glasses with side shields; fitted prescription where worker requires correction.Standard: AS/NZS 1337.1

Generate a SWMS that covers this hazard

Levvr's document generator turns this baseline into a jurisdiction-specific SWMS with the right Act, Regulations, and Codes of Practice for your state cited inline.

Start free trial